Block A:
- Facade filling with blocks and removing internal apartment partitions have been completed;
- Brick cladding of the old facade is in progress;
- Facade insulation and wood cladding work are ongoing;
- Balcony railings are being installed;
- Raised floor installation to the 5th floor is complete;
- "VIBRAFLOOR" insulation has been applied with a polyester layer that adheres to the tile as the lower layer of the raised floor;
- Facade cladding with orthotic coils is underway;
- Aluminum door and window installation up to the 2nd floor has been completed;
- Electrical wiring in apartments up to and including the 4th floor is finished;
- Elevator installation has begun.
Block B:
- Monolithic framework has been completed;
- Blockwork arrangement, both inside and outside the building, up to and including the 4th floor, is finished.
Block C:
- Reinforced concrete work for the foundation has been completed.