The construction of Arsenal Residence is actively underway

The construction of Arsenal Residence is actively underway

Block A:

  • Facade filling with blocks and removing internal apartment partitions have been completed;
  • Brick cladding of the old facade is in progress;
  • Facade insulation and wood cladding work are ongoing;
  • Balcony railings are being installed;
  • Raised floor installation to the 5th floor is complete;
  • "VIBRAFLOOR" insulation has been applied with a polyester layer that adheres to the tile as the lower layer of the raised floor;
  • Facade cladding with orthotic coils is underway;
  • Aluminum door and window installation up to the 2nd floor has been completed;
  • Electrical wiring in apartments up to and including the 4th floor is finished;
  • Elevator installation has begun.

Block B:

  • Monolithic framework has been completed;
  • Blockwork arrangement, both inside and outside the building, up to and including the 4th floor, is finished.

Block C:

  • Reinforced concrete work for the foundation has been completed.