The monolithic construction work on block A in the Arsenal residence has been completed

The monolithic construction work on block A in the Arsenal residence has been completed

In Block A, the following activities are ongoing:

  • Filling the facade with blocks, expected to be completed within 1 month.
  • Removal of partitions in apartments.
  • Facing the facade with old facade bricks.
  • Installation of balcony railings.
  • Installation of ventilation and fire safety systems.

In Block B:

  • Reinforcement of the vertical structure on the 2nd floor is underway, with molds being arranged and concreting in progress.