In block A, reinforcement work is underway for the vertical construction of the top floor, with forms being prepared and concrete pouring in progress; Block arrangement works are underway including on the 3rd floor; 90% of frame-monolithic construction works have been completed; The roofing slab on the 2nd level of parking at B block is in the process;
85% of the monolithic frame in block A has been completed. Foundation pouring in Block B has been completed and roofing work on the first level of the parking lot is underway.
Project construction is in an active phase. Currently, the arrangement of the slab foundation of the first residential floor is in progress.
Project construction is in active stage. Currently the arrangement of the slab foundation of the first residential floor is in progress