25 February 2025
Arsenal Residence Construction Is Actively Underway
Block A
- Cladding of the building with the old-style facade brick is underway
- Aluminium doors and windows are completed up to the 5th floor
- Screed flooring is completed on all floors
- Interior door installation is underway in the apartments
- Elevator installation is underway
- Power and electrical points are wired in every apartment
- Porcelain tile is being laid on the balconies
- Central heating installation is completed
- Renovation works can already begin in the apartments
Block B
- Cladding with the old-style facade brick is underway
- Internal utility works have begun
- Aluminium door and window installation will start soon
Block C
- The parking deck roofing works are completed