The monolithic construction work on block A in the Arsenal residence has been completed
The monolithic construction work on block A in the Arsenal residence has been completed

In Block A, the following activities are ongoing: Filling the facade with blocks, expected to be completed within 1 month. Removal of partitions in apartments. Facing the facade with old facade bricks. Installation of balcony railings. Installation of ventilation and fire safety systems. In Block B: Reinforcement of the vertical structure on the 2nd floor is underway, with molds being arranged and concreting in progress.

Director of Arsenal Residence Levan Karumidze on BMG broadcast
Director of Arsenal Residence Levan Karumidze on BMG broadcast

Levan Karumidze, director of the multi-functional complex Arsenal Residence, shared details about the project on BMG. The complex is prominently located in the Old Tbilisi district, just 650 meters from Sameba Cathedral, offering stunning views of old Tbilisi and Sameba. Notably, the architectural design of the complex seamlessly integrates with the historic charm of old Tbilisi. The new multifunctional complex comprises 4 blocks, with active construction of A and B blocks underway. Currently, 70% of the apartments have already been sold, with the company enticing customers through special summer promotions. Furthermore, the company's founder emphasizes the project's contribution to urban development, including plans for a recreational zone—a boulevard—on Arsenal Mountain.

The works in Arsenal Residence are in active mode
The works in Arsenal Residence are in active mode

A Block: • Roofing works of the last floor have been completed • The vertical construction of the terrace and duplex apartments on the last floor is being reinforced, molds are being made and concreting is in progress • Block arrangement works including the 3rd floor have been completed both inside and outside the building • 98% of the monolithic frame is completed • From the 4th floor to the 6th floor, the facade is being filled with blocks and internal partitions in the apartments are being built. • The old facade of the building is being covered with bricks B Block: • The pouring of the foundation and the roofing of both floors of the parking area have been completed. • The vertical construction of the commercial floor is being reinforced, molds are being made and concreting is in progress. Construction works are carried out by the company MBG

Georgian real estate exhibition At Expo Georgia- Arsenal Residence
Georgian real estate exhibition At Expo Georgia- Arsenal Residence

On April 26-28, at the construction and real estate exhibition held in Expo Georgia, GREA presented the Arsenal Residence project. The sales and marketing direction of the company is exclusively managed by GREA almost one year. Interest of the Arsenal Residence and the exhibition in general was quite high this year. Guests visiting our exhibition stands were informed of the project and the company's special offers. Arsenal Residence is a new outstanding multifunctional residential area in Avlabari, located 650 meters from the Trinity Cathedral. The construction of the project is in an active phase.

The construction work of A and B blocks in Arsenal Residence is underway.
The construction work of A and B blocks in Arsenal Residence is underway.

In block A, reinforcement work is underway for the vertical construction of the top floor, with forms being prepared and concrete pouring in progress; Block arrangement works are underway including on the 3rd floor; 90% of frame-monolithic construction works have been completed; The roofing slab on the 2nd level of parking at B block is in the process;

The construction work of A and B blocks in Arsenal Residence is underway
The construction work of A and B blocks in Arsenal Residence is underway

85% of the monolithic frame in block A has been completed. Foundation pouring in Block B has been completed and roofing work on the first level of the parking lot is underway.